日韩人妻无码一区二区三区久久99_日韩精品一区二区三区中文在线_无码日韩精品一区二区免费_久久久91精品国产一区二区三区_亚洲精品久久久一区黄无码_精品欧美一区二区在线观看欧美熟_精品一区二区高清免费观看_国产免费一区2区3区_国产日韩精品福利视频综合一区二区三区四区

Language:CHINESESENGLISH

Home > News > the construction quality steel welding acceptance of the relevant provisions
CONTACT US
  • Address:Pingtang Industrial District, Shipeng Village, Shishan Town, Nanhai District, Foshan City,
  • Phone:0757-81002668/0757-63323396
  • Fax:0757-81196682
  • Contact:Ben Zheng/13826981293 Kerry Lu/13751224830
  • E-mail:sbs@sbsprefabhouse.com
  • URL:http://m.applebabes.com

the construction quality steel welding acceptance of the relevant provisions

Time:[2016-1-27]  Hits:4848

Guangzhou Steel tells you: the construction quality steel welding acceptance of the relevant provisions

Guangzhou Steel tells you :( a) General provisions
Carbon structural steel should be cooled to ambient temperature in the weld, low-alloy structural steel welding should be completed after 24h, conduct inspection of welds.
(B) steel member Welding Engineering
1. Master Project
(1) Match rod, wire, flux, electroslag weld nozzles and other welding material and the base material shall comply with the design requirements and current national industry standard "construction steel welding procedure" JGJ81-2002; the electrodes, flux, medicine cored wire, melt in the mouth, etc. before use, should be required to its product specifications and welding process documents for baking and storage.
(2) welder must pass the examination and obtain a certificate. Certified welders welding must pass the examination in their projects and their scope of accreditation. Should fully examine all welders certificate and scope of accreditation, valid.
2. General Project
Weld feel should be achieved: a uniform shape, good shape, bead and bead between the bead and base metal transition smoother, welding slag and spatter basic clean.